Unique Group continues to conduct business as usual under a normal schedule, however, the safety and well-being of our employees and customers is always our highest priority. We are closely monitoring the Coronavirus pandemic and putting in place proactive measures to keep our communities safe and operational. Read more

Case Studies

For more information Enquire Now

Deck Cranes load tested in Singapore in 9 hours using Water Weights bags

Follow us
Client Leading independent ship management company
Country Eastern Anchorage, Singapore
Year July 2020
Service details WATER WEIGHTS® proof load bags can be used for testing cranes, beams, davits, or any lifting equipment and applied across the marine, industrial and engineering sectors. To know more, get in touch with us buoyancyballast@uniquegroup.com

Summary of the Project

Unique Group’s Buoyancy & Ballast team in Singapore successfully completed inspection & crane proof load testing of 4 Deck Cranes onboard the MV Falcon Bay vessel. The test was performed using 35T Water Weights bags by our engineers in line with the local COVID-19 safety measures.
The load testing operation was completed over a very short span of 9 hours over a weekend. 

Client Requirement

The client requested Unique Group to conduct inspection & crane proof load testing of 4 Deck Cranes onboard the MV Falcon Bay vessel. Each crane was to be tested with 35T water load.

Challenges faced

The client’s vessel urgently required the load test to be completed failing which the vessel was not allowed to sail. The client contacted the Unique Group team at the very last minute and requested for the job to be completed over the weekend. Our technicians had an early morning start in order to achieve the weekend deadline. A strong team spirit backed by technical expertise helped the team to mobilise the order and complete the load testing service as per schedule.

Unique Solution delivered

The load test operation on each crane was achieved in a quick, safe, and cost-effective manner using our 35t capacity Water Weights load testing bags. Over a very short span of 9 hours, the team fully assisted with the rigging, filling, testing, draining, and site clearance thereby marking the project completion in the safest and efficient manner. The load testing was also witnessed by a Classed Surveyor.

Above: Proof load testing in progress

Benefits delivered

  • The test was carried out on-site in a very safe and controlled environment
  • Quick time span to complete the test within the stipulated timelines as proposed by the client
  • Experienced technical team provided on-site support