Summary of the Project
Unique Group’s Buoyancy & Ballast division provided a comprehensive load measurement and data logging system to monitor the pull force of the winch during a high voltage cable lay.
Client requirement
Our client, a cable laying company, wanted us to provide a solution to monitor the pull force of the winch during a high voltage cable connection project under a 5km wide inland water in the south of the Netherlands. The solution was needed to ensure that, the pull force of the winch did not exceed the pull limit of the cable.
Unique solution delivered
Unique Group’s Buoyancy & Ballast division supplied a complete load measurement and data logging system which monitored the winch speed, cable payout and pull force. The pull force data was recorded for review and evaluation once the installation of this impressive length of high voltage cable was completed.
Benefits delivered
- Data review feature – The data logged in the system can be reviewed later
- Technical Expertise
- On-site Support